For immediate release 10/17/2025
NOTICE OF PAVEMENT RESURFACING

Information from TDOT and contractors:
Beginning Tuesday, October 21st, crews with Summers-Taylor will begin work on a pavement resurfacing project. The first step will consist of milling sections of three roads.

On Wednesday, October 22nd, crews will begin paving a segment (0.64 miles) of Erwin Highway from 11E to the Greeneville and Tusculum city-limit line.

When this section is complete, they will move paving operations to a 1.92-mile segment of Old Shiloh Road from Old Tusculum Road to Shiloh Road.

Next, paving will move to E Church Street to pave 1.2 miles between Bernard and Buckingham Drive (near Stratford Dr.).

The attached maps show the project areas.

We anticipate that all three roads will be paved within 2 weeks, weather permitting. Flagging operations will occur at all locations, with no closures anticipated. After the paving is complete, permanent striping will be installed.

As more information changes or becomes available, we will continue to share updates.
2 days ago, Town of Greeneville
E Church St work
Old Shiloh Road work
Erwin Highway work
FROM GREENEVILLE WATER COMMISSION 10/13/2025 NOTICE OF SEWER REHABILITATION WORK Project Update: Rehabilitation of manholes and paving will take place; however, all work will be flagged and scheduled to ensure that traffic flow is not affected in open areas. Location: Cleanup work will continue to be performed in previously completed areas. No road closures are anticipated in these locations; traffic will be flagged to allow vehicles to pass safely. Work will occur along: Charles Street Doughty Avenue W. McKee Street Main Street Kevin Lane Elm Street N. Main Street The project portion on Tateho Drive will continue through this week and is expected to be completed by Thursday, October 16, 2025. Morgan Contracting will also begin preparations for rehabilitation work on Thornwood Drive. Beginning Monday, October 13, 2025, both Tateho Drive and Thornwood Drive will be closed to traffic during active construction. Local access will be maintained for residents as conditions allow, but thru traffic will not be permitted. Project Information: Sewer rehabilitation work will begin on Monday, October 13, 2025, along the above-listed sections. Project Timeline: This phase of work is expected to take approximately two weeks, weather permitting. Traffic and Access Information: Thru traffic will not be permitted in active work zones. Residents and business patrons will maintain access to properties within the work zone where possible. Emergency vehicles will be provided access where possible. Additional Information: Work will progress in sections to minimize disruption. The contractor will make every effort to complete the work as quickly and safely as possible. Progress updates will be provided as the project moves forward. We appreciate your patience and cooperation as we continue to improve Greeneville’s infrastructure.
6 days ago, Christina Potts
Greeneville Water Commission
NOTICE 10/7/25: Use caution on W Main or choose another route. Pavement marking crews are preparing the road for the installation of snow-plowable reflectors.
12 days ago, Christina Potts
Pavement marking crew
Pavement Marking Crew
From the Greeneville Sun 10/4/25

Part of East Bernard Avenue to Close Tuesday (10/7/25) For Sewer Repair

The 300 block of East Bernard Avenue will be completely closed on Tuesday from East Church Street to Walnut Street, and coming toward downtown from Tusculum Boulevard for sewer main repairs. Traffic will be detoured to Walnut Street.

The closure will begin at 8 a.m., and the closure will continue until work is completed later on Tuesday.
13 days ago, Town of Greeneville
Greeneville Water Commission
TDOT UPDATE 10/6/2025

Starting tonight, 10/6, at 7 pm, crews will continue work on Main Street.

NO PARKING ON MAIN ST from McKee to Tusculum Blvd.

Crews will:
• Paint the permanent thermoplastic pavement markings (white/yellow lines, crosswalks, painted verbiage, etc)
• Install the snow-plowable reflectors
• Remove signs when all work is complete

The work should be completed in the next few days, if not tonight.
13 days ago, Town of Greeneville
Black road with yellow and white stripes and greenery on both sides
FROM GREENEVILLE WATER COMMISSION 9/26/2025 NOTICE OF SEWER REHABILITATION WORK Project Update: The construction phase on Charles Street and Tusculum Boulevard has been completed. These roads will remain open next week. Rehabilitation to the manholes and paving will take place; however, this work will be flagged and scheduled so that traffic flow is not affected. Location: Cleanup work will be performed in previously completed areas. No road closures are anticipated in these locations; traffic will be flagged to allow vehicles to pass safely. Work will occur along: Charles Street Doughty Avenue W. McKee Street Main Street Kevin Lane Elm Street N. Main Street Morgan Contracting will also mobilize to Tateho Drive. Due to the narrowness of this roadway, Tateho Drive will be closed to all traffic during the preparation and installation phases of the project. Project Information: Sewer rehabilitation work will begin on Monday, September 29, 2025, along the above-listed sections. Project Timeline: This phase of work is expected to take approximately two weeks, weather permitting. Traffic and Access Information: Thru traffic will not be permitted in active work zones. Residents and business patrons will maintain access to properties within the work zone. Emergency vehicles will be provided access where possible. Additional Information: Work will progress in sections to minimize disruption. The contractor will make every effort to complete the work as quickly and safely as possible. Progress updates will be provided as the project moves forward. We appreciate your patience and cooperation as we continue to improve Greeneville’s infrastructure.
23 days ago, Christina Potts
Greeneville Water Commission
There are a few spots left! Applications will be accepted until 5 PM Monday, September 29.

APPLY NOW for Citizens Academy, held on six Tuesday evenings: Sept. 30th to Nov. 4th, 2025 from 5:30-7:30 PM

https://www.greenevilletn.gov/page/citizens-academy

This free program provides an opportunity to learn important details of how our local government and Town departments operate, as well as a chance to tour facilities and ask questions. Though Town of Greeneville residents are given first priority for registration, being a resident is not required.

SUBJECT AREAS:

Administration & Marketing

Building, Planning, & Development

Finance / Recorder

Fire Department

Human Resources

Library

Mayor & City Council

Municipal Airport

Parks & Recreation

Police Department

Public Works

Roby Adult Center

Wellness
24 days ago, Town of Greeneville
Citizens Academy
REMINDER: Greeneville Water Commission has part of Tusculum Blvd near Justis Drive closed for sewer rehabilitation.

From Greeneville Water Commission 9/22/25
NOTICE OF SEWER REHABILITATION WORK
Location:
• Charles Street – From N Main Street to Irish Street
• Tusculum Boulevard – From Justis Drive to Hope Road
Project Information:
Sewer rehabilitation work will begin on Monday, September 22, 2025, along the above-listed sections.
Project Timeline:
This phase of work is expected to take approximately two weeks, weather permitting.
Traffic and Access Information:
• Thru traffic will not be permitted during this phase.
• Residents and business patrons will maintain access to properties within the work zone.
• Emergency vehicles will have access at all times.
Additional Information:
• A brief closure will occur where the work intersects with N Main Street; this section will be reopened as quickly as possible.
• Work will progress in sections to minimize disruption.
• The contractor will make every effort to complete the work as quickly as possible.
• Progress updates will be provided via email throughout the duration of this phase.
We appreciate your patience and cooperation as we work to improve Greeneville’s infrastructure.
24 days ago, Town of Greeneville
Greeneville Water Commission
TDOT UPDATE 9/23/25:

Please see below for the updates:

9/24 and possibly 9/25 – Finish Paving Side Roads
9/29 – Mill under railroad bridge and nearby side roads
9/30 – Pave under railroad bridge and nearby side roads

Work yet to be scheduled but that is set to be completed prior to October 31st
• Paint the permanent thermoplastic pavement markings (white/yellow lines, crosswalks, painted verbiage, etc)
• Install the snowplowable reflectors
• Remove signs when all work is complete
26 days ago, Town of Greeneville
Main Street
From Greeneville Water Commission 9/22/25
NOTICE OF SEWER REHABILITATION WORK

Location:
• Charles Street – From N Main Street to Irish Street
• Tusculum Boulevard – From Justice Boulevard to Hope Road

Project Information:
Sewer rehabilitation work will begin on Monday, September 22, 2025, along the above-listed sections.

Project Timeline:
This phase of work is expected to take approximately two weeks, weather permitting.

Traffic and Access Information:
• Thru traffic will not be permitted during this phase.
• Residents and business patrons will maintain access to properties within the work zone.
• Emergency vehicles will have access at all times.

Additional Information:
• A brief closure will occur where the work intersects with N Main Street; this section will be reopened as quickly as possible.
• Work will progress in sections to minimize disruption.
• The contractor will make every effort to complete the work as quickly as possible.
• Progress updates will be provided via email throughout the duration of this phase.

We appreciate your patience and cooperation as we work to improve Greeneville’s infrastructure.
27 days ago, Town of Greeneville
Greeneville Water Commission
TDOT UPDATE 9/18/2025 Main Street Repaving 9/18 – Mill from southbound SR35 from Mckee to SR70 9/19 – Mill from SR70 to Ricker Ave; Pave the remainder of SR35 9/22-9/23 – Pave if any of the mainline, side roads, parking areas remain Work yet to be scheduled but that is set to be completed prior to October 31st: Paint the permanent thermoplastic pavement markings (white/yellow lines, crosswalks, painted verbiage, etc) Install the snowplowable reflectors Remove signs when all work is complete
about 1 month ago, Christina Potts
Main Street

Town of Greeneville Citizens Academy

APPLY NOW for Citizens Academy, held on six Tuesday evenings: Sept. 30th to Nov. 4th, 2025 from 5:30-7:30 PM

https://www.greenevilletn.gov/page/citizens-academy


This free program provides an opportunity to learn important details of how our local government and Town departments operate, as well as a chance to tour facilities and ask questions. Though Town of Greeneville residents are given first priority for registration, being a resident within the city limits is not required.

SUBJECT AREAS:

Administration & Marketing

Building, Planning, & Development

Finance / Recorder

Fire Department

Human Resources

Library

Mayor & City Council

Municipal Airport

Parks & Recreation

Police Department

Public Works

Roby Adult Center

Wellness

about 1 month ago, Town of Greeneville
Citizens Academy Subject Areas
Citizens Academy - sign up now
TDOT Supplemental Update 9/14/2025

9/15 – Pave Parking Areas and Side Roads

9/16 and 9/17 – No work

9/18 – Mill the remainder of SR35

9/19 – Pave the remainder of SR35

9/22-9/23 – Pave if any of the mainline, side roads, parking areas remain
about 1 month ago, Town of Greeneville
TDOT UPDATE 9/11/2025

The contractor brought a second milling machine to expedite this work, so the current progress has outpaced the last schedule update. Additionally, the contractor will not be working on the SR35 resurfacing next Tuesday and Wednesday.

9/11 and 9/12; 9/15 – Pave SR35 NB From Tusculum Blvd (today); Mill and Pave SB SR35 from 11E to near the SR350 Intersection

9/16 and 9/17 – No work

9/18 and 9/19 - Mill and Pave SB SR35 from near the SR350 Intersection to Ricker Avenue

9/22-9/24 – Pave SR35 if any of the mainline remains; pave side roads
about 1 month ago, Town of Greeneville
Resurfacing
TDOT UPDATE: 9/11/2025
11E / Snapps Ferry Bridge Rehabilitation Contract

Prime Contractor is King General Contractors
Contract Completion Date is 6/15/2026

Progress Status:
Currently working under the bridge from Snapps Ferry and in the TDOT ROW between the ramps and 11E. The contractor plans to close the right northbound lane on Snapps Ferry starting 9/11/2025

Although the lane closures will alternate on Snapps Ferry, two lanes will be open at all times (one lane each direction)

It will likely be several months, but 11E at the bridge will be reduced to one lane each direction when the contractor begins working on the bridge deck

All four lanes on Snapps Ferry are to remain open while the 11E lane closures and wide load detour are in place

To keep up to date on TDOT projects, visit SmartWay:
https://smartway.tn.gov/traffic
about 1 month ago, Town of Greeneville
11E Bridge Work
NOTICE: Please obey the message boards and do not park on Main Street! Parked cars stall the resurfacing project and may be towed at the owner's expense
about 1 month ago, Christina Potts
No parking
FROM GREENEVILLE WATER COMMISSION 9/9/2025 MAINTENANCE SHOP WILL HAVE A PORTION OF HOPE ROAD COMPLETELY CLOSED ON 09/11/2025 FROM THE INTERSECTION OF TUSCULUM BOULEVARD/TEMPLE STREET DETOURING TRAFFIC OUT TEMPLE STREET AND ALSO DETOURING AT HOPEVILLE AVENUE AND DOGWOOD DRIVE FROM 8:00 AM UNTIL JOB IS COMPLETED ON THE DAY FOR A WATER TAP FOR A NEW WATER LINE REPLACEMENT DOWN ROBINHOOD ROAD. CUSTOMERS THAT LIVE ON THIS SHORT CLOSURE WILL BE ALLOWED ACCESS TO THEIR HOMES FROM EITHER DIRECTION. IF YOU HAVE ANY FUTHER QUESTIONS FEEL FREE TO JEFF OR WILLIAM MON-FRI 7AM TO 3PM DAILY @ 1-423-798-2040.
about 1 month ago, Christina Potts
GWC logo
TDOT UPDATE 9/9/2025 Please see below for the updated tentative milling and paving schedule: 9/9 to 9/12 – Mill and Pave SR35 Northbound from downtown section to US11E 9/15 to 9/19 – Mill and Pave SR35 Southbound from US11E back to Ricker Avenue At this point, the milling operation is just working towards the end of the job at 11E with the paving operation falling in directly behind. Once we reach 11E, the milling and paving will start working back to where the project starts art Ricker Ave.
about 1 month ago, Christina Potts
Milling Main Street
FROM GREENEVILLE WATER COMMISSION 9/4/2025 NOTICE OF SEWER REHABILITATION WORK Location: Doughty Avenue – From N Main Street to Irish Street Charles Street – From N Main Street to Irish Street W McKee Street – From N Main Street to Irish Street Project Information: Sewer rehabilitation work will begin on Monday, September 8, 2025, along the above-listed sections. Project Timeline: This phase of work is expected to take approximately two weeks, weather permitting. Traffic and Access Information: Thru traffic will not be permitted during this phase. Residents and business patrons will maintain access to properties within the work zone. Emergency vehicles will have access at all times. Additional Information: A brief closure will occur where the work intersects with N Main Street; this section will be reopened as quickly as possible. Work will progress in sections to minimize disruption. The contractor will make every effort to complete the work as quickly as possible. Progress updates will be provided via email throughout the duration of this phase. We appreciate your patience and cooperation as we work to improve Greeneville’s infrastructure. Contact Information: On-Site Representative: 423-552-3098 Greeneville Water Commission Main Office: 423-638-3148
about 1 month ago, Christina Potts
GWC logo
TDOT UPDATE 9/4/2025 The start dates are still correct, but the plan for the milling and paving has been altered. The contractor no longer plans on milling and paving in sections but rather complete all of the Northbound lane then move on to the Southbound side. Please see below: 9/5 – Mill SR35 (Main line and side roads) starting at Ricker Avenue with the intention to mill the NB side to end of job at 11E 9/8 – Pave milled sections; continue milling on SR35 towards 11E intersection 9/9 – Continue progress on milling with paving operations falling in behind
about 1 month ago, Christina Potts
TDOT area of work